In progressOn site now

Plant room pipework replacement

Phased replacement of forty-year-old distribution pipework across a live commercial building.

Sector
Commercial
Programme
7 weeks
Started
2026
Phase
3 of 4
The job

Forty years of patch repairs had left the plant room with more joints than original pipe. We are replacing the distribution runs in phases so no floor is ever without water for more than a working day.

Phases one and two are complete and commissioned. Phase three — the riser to floors five through nine — is on site now, with the final valve set scheduled for the week after.

Fixing PipesPreventative maintenance
What it involved
  1. 01

    Survey and phased replacement plan

  2. 02

    Distribution run replacement, floors 1–4 (complete)

  3. 03

    Riser replacement, floors 5–9 (in progress)

  4. 04

    New isolation valve sets throughout

  5. 05

    Commissioning and as-built drawings

Client

Commercial landlord

Location

Etobicoke, ON

Next project

Retirement home water system upgrade

Markham, ON

Got something similar?

Send us the details and we will come back with an upfront quote. For anything urgent, calling is always fastest.

Make appointment

Fill out the form to schedule your appointment with our expert team. We’ll confirm your time and address your plumbing needs promptly.

  • Affordable pricing & fast service
  • 16 years of experience
  • Fully licensed and insured
  • 100% Customer satisfaction

We reply to every request. For urgent work, calling is always fastest.

Call nowBook a visit